Regents Canal, Camden Rail Bridge Replacement Bridge Support
Overview
- Client: Story Contracting
- Project Value: £315k
- Dates: December 2022 – January 2023
GPS Marine and Civil Services (GPS MACS) provided marine support to Story Contracting during the possession and replacement of the Camden rail bridge over Christmas 2022.
The scope of work included constructing a solid pontoon deck across the width of the Regents Canal. The barges were fitted with a crash deck to allow the demolition teams safe access to the underside of the bridge and ensure no waste from the demolition went into the waterways.
During the constructive stage the pontoon was used to support the entire weight of the new bridge planks and jack into position for the securing of the final deck beam.
As part of the works GPS MACS undertook detailed stability calculations to account for the movement of the barge during the uneven loading of the bridge planks. With the barge expected to drop over 200mm during loading and only a limited run on the jacks these calculations were essential to the timely reconstruction of the bridge.
Upon loading of bridge planks, the barge behaved as GPS MACS calculated and all the planks aligned allowing for the Story team to lift in the final section using the 650t land-based crane.
GPS operatives worked 24 hours during the possession in support of the project, maintaining barge stability levels by ballasting in line with the stability calculations. This work allowed the barge works to complete on schedule and Story to successfully hand back the bridge to Network Rail on time.
Enabling Works
Pre-construction canal bathymetry survey
Detailed pontoon loading calculations including under up to 30t demo waste and during the support of the new bridge under loading.
Marine Works
Assembly of pontoon system in adjacent basin and transfer and secure in place
Provide safe access platform to the underside of the bridge for demolition teams
Manage ballast levels to ensure barge stability is within calculated limits before and during demolition.
Mange ballast levels to ensure barge stability during the bridge construction allowing for exact alignment of all bridge panels.
Design
Detailed barge behaviour analysis under variation of loads
Construction
Complete construction of the full scope of works
Project Management
Coordination with multiple contractors on a high time constrained job in a high visibility location
Engineering
Stability analysis for the barges
Deck loading analysis for the barges
Marine Logistics
Planned, supervised, and carried out mobilisation of all marine plant to site.
Utilised the following key sites for supporting the project:
Powerdays, Wilsden
Camden, Regents Canal