Regents Canal, Camden Rail Bridge Replacement Bridge Support

Story Contracting

Project Value:

£315k

Dates:

December 2022 – January 2023

Related News

Coming Soon

Overview

GPS Marine and Civil Services (GPS MACS) provided marine support to Story Contracting during the possession and replacement of the Camden rail bridge over Christmas 2022.

The scope of work included constructing a solid pontoon deck across the width of the Regents Canal. The barges were fitted with a crash deck to allow the demolition teams safe access to the underside of the bridge and ensure no waste from the demolition went into the waterways.

During the constructive stage the pontoon was used to support the entire weight of the new bridge planks and jack into position for the securing of the final deck beam.

As part of the works GPS MACS undertook detailed stability calculations to account for the movement of the barge during the uneven loading of the bridge planks. With the barge expected to drop over 200mm during loading and only a limited run on the jacks these calculations were essential to the timely reconstruction of the bridge.

Upon loading of bridge planks, the barge behaved as GPS MACS calculated and all the planks aligned allowing for the Story team to lift in the final section using the 650t land-based crane.

GPS operatives worked 24 hours during the possession in support of the project, maintaining barge stability levels by ballasting in line with the stability calculations. This work allowed the barge works to complete on schedule and Story to successfully hand back the bridge to Network Rail on time.

Other Projects

Levens Viaduct
Network Rail
Project Type: Maintenance and Repair

Project Duration: Jul 2024
READ MORE
Oikos Fuel Transfer Jetty 2 Repairs
Oikos Storage Ltd
Project Type: Maintenance and Repair

Project Duration: August 2023 – September 2023
READ MORE
Nearshore / Inland Warerways

Working on a high traffic high visibility site in the centre of Camden Central London.

Health and Safety

Provided a solid platform to allow demolition teams to erect scaffold to work on the underside of the rail bridge during demolition, massively reduced risk of from working from a canal barge at height .

Environmental

System allowed for zero demo waste into the canal

Innovation

Original temporary works designers explored the use of barges to support the bridge, but were unable to achieve adequate stability and levels for jacking. GPS MACS able to achieve excellent stability due to the calculated redistribution of ballast across the pontoon system, allowing for maintained levels even during uneven loading.

Story Contracting

Project Value:

£315k

Dates:

December 2022 – January 2023
PREVIOUS
London City Island
NEXT
Fambridge Yacht Haven, River Crouch

Overview

GPS Marine and Civil Services (GPS MACS) provided marine support to Story Contracting during the possession and replacement of the Camden rail bridge over Christmas 2022.

The scope of work included constructing a solid pontoon deck across the width of the Regents Canal. The barges were fitted with a crash deck to allow the demolition teams safe access to the underside of the bridge and ensure no waste from the demolition went into the waterways.

During the constructive stage the pontoon was used to support the entire weight of the new bridge planks and jack into position for the securing of the final deck beam.

As part of the works GPS MACS undertook detailed stability calculations to account for the movement of the barge during the uneven loading of the bridge planks. With the barge expected to drop over 200mm during loading and only a limited run on the jacks these calculations were essential to the timely reconstruction of the bridge.

Upon loading of bridge planks, the barge behaved as GPS MACS calculated and all the planks aligned allowing for the Story team to lift in the final section using the 650t land-based crane.

GPS operatives worked 24 hours during the possession in support of the project, maintaining barge stability levels by ballasting in line with the stability calculations. This work allowed the barge works to complete on schedule and Story to successfully hand back the bridge to Network Rail on time.

Nearshore / Inland Warerways

Working on a high traffic high visibility site in the centre of Camden Central London.

Health and Safety

Provided a solid platform to allow demolition teams to erect scaffold to work on the underside of the rail bridge during demolition, massively reduced risk of from working from a canal barge at height .

Environmental

System allowed for zero demo waste into the canal

Innovation

Original temporary works designers explored the use of barges to support the bridge, but were unable to achieve adequate stability and levels for jacking. GPS MACS able to achieve excellent stability due to the calculated redistribution of ballast across the pontoon system, allowing for maintained levels even during uneven loading.