Fambridge Yacht Haven Pile Replacement

Yacht Havens Group

Project Value:

£430,000

Dates:

April 2023 – May 2023

Related News

Coming Soon

Overview

Fambridge Yacht Haven (FYH) engaged GPS Marine and Civil Services (GPS MACS) to undertake replacement of the piles holding their vessel access pontoons in place across their two marinas at the River Crouch Facility.

As part of the scope GPS MACS also replaced both the access gangways to the East and West marina pontoons.

Working from the GPS Boxer Crane Barge and using vibration and air hammer piling GPS MACS removed old timber and steel piles across a 5-week duration, finishing 3 weeks ahead of schedule, massively reducing the impact on the marina leisure boat users.

Other Projects

Oikos Fuel Transfer Jetty 2 Repairs
Oikos Storage Ltd
Project Type: Maintenance and Repair

Project Duration: August 2023 – September 2023
READ MORE
Fambridge Yacht Haven, River Crouch
Project Type: Maintenance and Repair

Project Duration: Project still in progress
READ MORE
Nearshore / Inland Warerways

Working within FYH Crouch Marina, an extremely tight area for the Boxer barge to be operating

Environmental

Due to the sensitive nature of the surrounding environment, the marine licence restricted heavy construction during the winter months meaning we were forced to schedule the works during the spring when the marina was busiest.

Net Zero

Mobilisation of all piles and piling materials by barge. Removal from site of all timber and steel piles as well as the two replaced gangways by barge. Estimated trucks removed form roads: 20

Yacht Havens Group

Project Value:

£430,000

Dates:

April 2023 – May 2023
PREVIOUS
Fambridge Yacht Haven, River Crouch
NEXT
Oikos Fuel Transfer Jetty 2 Repairs

Overview

Fambridge Yacht Haven (FYH) engaged GPS Marine and Civil Services (GPS MACS) to undertake replacement of the piles holding their vessel access pontoons in place across their two marinas at the River Crouch Facility.

As part of the scope GPS MACS also replaced both the access gangways to the East and West marina pontoons.

Working from the GPS Boxer Crane Barge and using vibration and air hammer piling GPS MACS removed old timber and steel piles across a 5-week duration, finishing 3 weeks ahead of schedule, massively reducing the impact on the marina leisure boat users.

Nearshore / Inland Warerways

Working within FYH Crouch Marina, an extremely tight area for the Boxer barge to be operating

Environmental

Due to the sensitive nature of the surrounding environment, the marine licence restricted heavy construction during the winter months meaning we were forced to schedule the works during the spring when the marina was busiest.

Net Zero

Mobilisation of all piles and piling materials by barge. Removal from site of all timber and steel piles as well as the two replaced gangways by barge. Estimated trucks removed form roads: 20

Menu