Southend Pier Extension
Overview
- Client: Southend-On-Sea Council
- Project Value: £700,000
- Dates: July – Sept 2021
The purpose of the project was to provide structural support to the proposed toilet block and viewing gallery on Southend Pier. Due to the nature of the proposed toilet block that is intended to “sit” on the pier, the existing pier structure was considered insufficient to support the proposed load. The new toilet block sits on the same footprint as a previously demolished toilet block, the original structure was supported by timber cantilever beams which are deemed structurally insufficient; therefore a new steel structure was proposed.
The project was carried out on behalf of Southend-on-Sea Borough Council and is a part of the £2.5million capital investment into Southend-on-Sea’s pier head, following engagement with residents and visitors.
GPS MACS were awarded the works as Principle Contractor. The challenging site required detailed planning and precision execution, working alongside the Grade 2 listed Pier and 1.5km off the coast.
Enabling works and mobilisation
UXO survey and clearance works using our in house dive team
Mobilise barges, plant and equipment from Port of Tilbury to site
Set up site hoarding, access, services protection, and strip existing handrailing and walkway
Site works to existing elements
Install temporary works and complete modification works to existing steel and pile heads
Site works for new elements
8 no. marine piles installation
Installation of new and replacement steelwork
Install new secondary steel, deck beams and floor plates
Handover and demobilisation
Reinstate decking, handrail and remove all plant, equipment from site
Tow barges back to Port of Tilbury for demobilisation
Design
Design of the marine piles and supporting steelwork
Design of the bracing steelwork to replicate the existing Grade 2 listed structure
Construction
Complete construction of the full scope of works
Project Management
Obtain the necessary river works licences from the river regulators: Port of London Authority, Environmental Authority and the Marine Management Organisation.
Management of delivery, from design stage through to construction and commissioning.
Engineering
Stability analysis and deck loading analysis for the barges through our supply chain Red 7 Marine.
Planned, supervised, and carried out all lifting operations on site
Design and installation of temporary works, namely pile gates and access walkways
Site engineering including quality assurance, setting out and surveying, drawings, coordinating works and planning of operations
Marine Logistics
Precision positioning of the barges alongside the Grade 2 listed pier. Mooring barges used 4 point anchor system along with spuds for additional measures.
Planned, supervised and carried out mobilisation of all marine plant to site. Including floating crane transfers.
Delivery of material barges
Works completed using support craft such as tugs and multicats