Skip to main content
header-curve
Maintenance & Repair

Wapping boat yard cladding replacement

Overview

  • Client: SW Bruce and Co Ltd
  • Project Value: £1.1m
  • Dates: Feb 24 - Mar 24

GPS MACS conducted an inspection of the cladding system at 78 - 80 Wapping High St, which is the Thames River Police Boatyard. The cladding panels were installed prior to 1973 when the boatyard was opened, and overall, the installation was found to be run down and aged. However, it has lasted for longer than the forecast lifecycle of materials used for these applications, within these climatic conditions. 

Two panels had fallen from the south elevation into the river. Also, we identified numerous panels where the weather strips between panels had either been dislodged or fallen from position. GPS MACS were commissioned to carry out replacement works to the south elevation system. 

Wapping sits on the north bank of the river Thames in the borough of Tower Hamlets in east London. Conveniently Wapping is east of Tower bridge making towage of crane barges to site safer and reducing operational risks.

The biggest challenge faced on this project was the condition of the structure that we had to install the panels on, after years of decay the structure was rotting and the timber frame needed replacing in order to facilitate installing the new panels. 

We were appointed on the project as the marine contractor: 

  • Mobilisation of barge

  • Dismantle and dispose of existing damaged area on south elevation 

  • Remove existing panels to 2 x panels, analyse materials, dismantle subframe and supports

  • Installation and commissioning of the following:                         

    • Install2 units of subframe bracketry                               

    • Install 2 no. of facia panels                                

    • Install 2no. of soffit details                                

    • Install 20 no. of weather strips                           

  • General marine operations including:

    • Control measures for operating marine plant 

    • Lifting operations from barges

    • Site (barge) access via personnel vessels

    • Towage / Movement of barges for mobilisation / demobilisation

    • Towage / Movement of barges within the site specific boundaries

    • Mooring / Spudding of crane barges

    • Crane barge general operations

    • Mooring of supply barges and vessels

    • Emergency procedures

    • Working over water safe working principles

    • General vessel movements within the Port of London Authority (PLA) channels

 

Project delivery 

  • We were employed as the marine contractor with overall responsibility for the safe and effective delivery of the marine works on the site. 

Engineering 

  • Stability analysis for the barges 

  • Planned, supervised, and carried out all lifting operations on site.

  • Setting out and surveying, drawings, coordinating works and planning of operations

  • Post installation inspection and testing ensuring no water penetration. 

Marine Logistics 

  • Planned, supervised and carried out mobilisation of all marine plant to site. Including crane barge.

Construction

  • Install subframe bracketry 

  • Install Facia panels

  • Install Soffit 

  • Install weather strips

Demolition

  • Removal of existing panels

  • Dismantle subframe and supports

Main Image
Main Image
Main Image
Main Image